Project name: Wastewater treatment and reuse project of Cuimen fixed-point plating industrial base in Jiangmen
Project honors: The largest electroplating base in China, the second national electroplating park seminar platform
Construction scale: Phase I 5000m/d, total designed water volume 30000m/d
Construction time: Phase I completed and put into trial operation in 2011
Emission standards: Implement the most stringent special emission limits in GB21900-2008 Table 3 of the electroplating industry, with a reuse rate of 70% and effluent COD <50mg/L, Cu <0.3mg/L, Ni <0.1mg/L
Service content: Engineering design, general contracting, commissioning
Park environmental protection facility operation and management
Core technology:
XDS electroplating wastewater treatment technology
XTM park intelligent technology management system
MBR process. Double membrane reuse system